Proposed Extension Timeline

St Andrews Primary School

Proposed Extension and Alterations Initial Programme

Scheme design and Consultation Apr 2017 to May 2017

Planning Submission May 2017 to Jul 2017

Building Warrant Jan 2018 to Mar 2018

Detail Design May 2017 to Mar 2018

Contract Documentation and Tender Contractor Jan 2018 to Mar 2018

Construction Procurement Mar 2018 to July 2018

Construction Jul 2018 to Feb 2020*

*Subject to confirmation of final phasing in order to minimise disruption.